DIN standards for C-shaped retaining rings fitted into shaft grooves (471) and bore grooves (472). They include both regular and heavy types and are current. The domestic KS B 1336 and Japanese JIS B 2804 are of the same kind.

Status: Current

Key points

  • DIN 471 (for shafts) and DIN 472 (for bores) are current DIN and specify both the regular type and the heavy type. For both standards, the new edition of May 2026 (5/2026) is current.
  • They also specify the dimensions of the groove in which the ring is fitted. They are used to fix parts such as bearings on a shaft or in a bore and to take axial force.
  • The nominal size of a shaft ring is the shaft diameter, and that of a bore ring is the bore diameter.
  • National standards of the same kind are KS B 1336 (C-type retaining rings) and JIS B 2804 (止め輪). E-rings are KS B 1337 · DIN 6799.
  • DIN 471 and 472 are current DIN not replaced by ISO.

Checks for BOMs and buying

  • For a line that only says "snap ring", determine whether it is for a shaft or a bore. If the lugs are outside, it is for a shaft; if inside, for a bore.
  • Do not assume that KS and JIS rings have the same dimensions as DIN rings. Check the groove dimensions as well.
  • A ring that has been spread and removed may change shape, so replacing it with a new one at maintenance is generally done.

Equivalent and superseding standards

  • KS B 1336 KS C-type retaining ring (dimension comparison not included)
  • JIS B 2804 Japan 止め輪

Korean Standards (KS): official search ↗ · JISC: official search ↗ · DIN: official search ↗

These links go to the issuing bodies; they are not the verification source of individual values.

Basis: DIN 471 · DIN 472 · KS B 1336 · JIS B 2804 · library-wide review 2026-10 (no per-item review date). Project edition, tolerances and service conditions must be confirmed against the standard text and supplier documents. Do not estimate unconfirmed values.